Receiving Inspection and Storage
Products are typically delivered on pallets or otherwise suitable for handling with forklifts or pallet trucks. Packaging is designed to withstand transport and site storage in accordance with manufacturer guidelines.
After delivery, the customer is responsible for immediate protection. Packaging materials are not sufficient against weather or site conditions.
Check:
- Number of packages
- Condition of packaging
- Glass integrity
Document any damage:
- Take photos
- Record in delivery note
Transport company is not liable for unrecorded damage.
Always lift using proper supports – never directly with slings.
Store:
- On level surface
- In stable temperature and humidity
- Protected from sunlight
Fire-rated windows are sensitive to UV exposure.
Store upright, not leaning.
Do not install before interior concrete work is completed and dried.
Do not use windows as passageways for:
- Materials
- Cables or hoses
Support remaining units when unpacking.
Supplier is not responsible for construction-related damage.
Installation Instructions
If a control unit is included:
- Store safely
- Inform electrician
Note:
- Glass label dimensions refer to glass only
- Frame depth excludes sash
- Sash extends 37 mm outward
Always use:
- Spirit level
- Measuring tape
Do not install if defects are found.
Install windows at a late construction stage to minimize exposure.
Verify specifications against drawings.
Measure opening:
- Should be 20–40 mm larger than frame
Do not remove sash:
- Voids CE marking and warranty
Lifting
Use supports when lifting with crane.
Pallets are not designed for lifting.
Ensure stability of remaining units.
Use suction lifters where applicable.
Check center of gravity.
Do not use suction on coated glass (Activ / AC).
Installation
Install support blocks or leveling screws.
Check level.
Position frame and secure temporarily.
Fix using:
- Frame screws (recommended 6 × 80–150 mm)
Ensure free sash movement.
Check:
- Top frame not sagging
- Bottom frame not bowing
Check diagonals.
PERFORM FUNCTION TEST BEFORE INSULATION!
Electrical Test
Control unit includes 1–2 batteries.
If two:
- Connect in series
Connect actuator:
- Brown (+)
- Blue (−)
Reverse polarity to close.
Stop immediately if obstruction occurs.
Insulation
Recommended:
- Mineral wool
Foam:
- Use cautiously
One-component foam is prohibited.
Check wide frames for deformation.
Multiple Windows
Allow 10 mm tolerance between units.
Use insulation strip.
External Finishing
- No obstruction to sash movement allowed.
- Do not attach anything to sash.
- Install flashing to Z-profile.
- Re-test after installation.
- Opening distance up to 1100 mm.
Electrical Installation
Electrician connects and tests system. Cable routing: Above window, centered
For support, contact customer service: +35810 322 2700.